Permitting procedures in renewable energy project development

Permitting procedures in renewable energy project development

Project development for renewable energy requires structured permit management. As experts at LEKO ENERGY, we guide wind energy projects through every phase of the permitting process. Our experience from numerous successful projects shows that professional permit management speeds up procedures and increases the chances of approval. This overview gives you an insight into the various permitting procedures and their requirements.

BImSchG permit: the central basis

The BImSchG permit is the core of the permitting procedure. The application must contain all the documents required under the Federal Immission Control Act (BImSchG). These include noise forecasts, shadow flicker assessments and distances to residential buildings. The permitting authority checks the documents for completeness and coordinates the involvement of the specialist authorities. For complete applications, the processing time is seven months. Careful preparation of the application and early coordination with the permitting authority optimise the procedure.

Nature conservation permits

Nature conservation imposes specific requirements on the permit. Species protection surveys must be carried out over a full year. Breeding birds are mapped between March and July. Bat surveys run from April to October. The surveys include:

  • Spatial use analyses for species sensitive to wind power
  • Breeding bird mapping within a radius of 1,000 metres
  • Migratory bird surveys
  • Bat activity at different heights
  • Habitat analyses of protected species

The entire nature conservation assessment takes at least 12–15 months. Migratory bird routes are a sensitive issue: although they cannot be changed, modern operating concepts offer solutions. Technical measures such as shutdown algorithms or detection systems make it possible to operate turbines even in critical areas.

Nature conservation assessments are not obstacles but signposts for sustainable project planning. They show how wind turbines and nature conservation can work together in harmony. The survey results provide valuable guidance for optimal turbine planning. This approach produces projects that combine climate protection and species protection.

LEKO ENERGY: expertise in wind farm planning

LEKO ENERGY supports you with sound know-how in all permitting procedures. Contact us for an initial consultation about your wind energy project.

Write us an email (opens your email program)

Building law and land use

The building permit examines whether the project is compatible with municipal planning. A key point: the land must be designated for wind energy. The land use plan and the development plan must permit the construction of wind turbines.

The processing time for building permits averages 3–4 months. The application requires a site plan showing setback areas, construction drawings of the turbine, proof of structural stability, a fire protection concept, access and utilities planning, type certification of the wind turbine and a noise immission forecast.

These documents should be reviewed as early as the preliminary planning phase. Project development for renewable energy takes the following into account:

  • Distances to residential areas
  • Access and access roads (at least 4.5 metres wide)
  • Fire protection requirements (distances, firefighting equipment)
  • Structural verification (soil survey required)

Early coordination with the building authority – ideally 6 months before submitting the application – considerably increases the chances of approval.

Grid connection and technical permits

The grid connection requires a separate approval from the responsible grid operator. Processing takes between 6 and 8 months. The application must contain detailed technical information on the electrical output and the feed-in point, a grid compatibility assessment, a protection concept, transformer data and the planned cable layout and route planning.

The technical planning must comply with the current grid connection conditions. The grid operator checks the available grid capacity and sets technical requirements. The review begins with a preliminary grid compatibility study, followed by a detailed technical assessment. The connection conditions and technical connection rules are then defined.

Coordination with the grid operator should take place in parallel with the BImSchG permit. An early grid connection application secures feed-in capacity. Technical adjustments are possible during the procedure.

Permitting procedures in renewable energy project development: construction site of a wind farm

Special features in the federal states

Permitting procedures differ between the federal states. Brandenburg relies on a central permitting authority for wind turbines. This enables faster procedures through specialised teams. Lower Saxony assigns responsibilities at district level. Baden-Württemberg uses a two-stage procedure comprising spatial planning and permitting.

Each federal state has developed its own requirements for wind turbines. Bavaria imposes special requirements with its 10H rule: the distance to residential buildings must be at least ten times the height of the turbine. For a 200-metre turbine, this means a minimum distance of 2,000 metres.

These regional differences call for an adapted planning strategy. Experience with the respective authorities and their requirements speeds up the procedure. Professional permit management takes these particularities into account from the start of the project.

Conclusion

The permitting procedures in renewable energy project development require detailed specialist knowledge and experience. From the BImSchG permit and nature conservation to technical requirements, every procedural step must be precisely planned and implemented. This article covers only a small selection of the permits required. The processing time for all permits is 18 to 24 months.

Would you rather not face all these challenges alone? Solving problems after the fact costs time and money. Early professional planning saves both. LEKO ENERGY supports you with sound know-how in all permitting procedures. Contact us for an initial consultation about your wind energy project.

WE ARE HERE FOR YOU

Contact us

Potsdam
LEKO ENERGY GmbH Kirschallee 65 14469 Potsdam
Augustin Köllner
Sijar Hamid
Dr. Hannes Lenz
Tilman Herweg