Construction of a wind turbine

Building a wind turbine

As energy prices rise, interest in renewable energy sources such as wind power is growing rapidly. Around 62.7% of Germany’s electricity already comes from renewable sources, and the share of wind power is set to exceed 65% by 2030. These figures not only underline the ambitious emission reduction targets but also demonstrate the economic benefits of switching to green energy. Wind projects help to reduce dependence on imported fuels while stabilising energy prices.

Today, wind turbines are built by large energy companies as well as by smaller businesses, farmers and private individuals. For them, it is a way to reduce energy costs and shape the future through a sustainable energy supply. Together with its partners, our company offers a comprehensive range of services for every construction phase. Our specialists develop tailored solutions for every type of wind project that meet each client’s individual requirements, and assist in obtaining all the necessary permits to pave the way for implementation.

Building a wind turbine: engineers and construction workers inspecting a wind turbine

Construction phases of a wind turbine

Building a wind turbine involves several carefully planned phases that ensure the turbine operates efficiently and remains stable over the long term. Each phase requires specific resources and expertise to achieve optimum results. These are the key steps to consider when building a wind turbine:

  • Building access roads and preparing the site: Reliable and stable infrastructure is essential for the construction and maintenance of the turbine. Access roads must be designed so that heavy construction machinery and transport vehicles can reach even remote regions without difficulty.
  • Erecting operational buildings and facilities: These buildings and facilities are used to control and monitor the turbine and must be weatherproof and durable. They house the necessary control equipment and the connection to the power grid.
  • Foundation work, delivery and installation of the wind turbines: The foundation forms the backbone of the installation. A stable foundation is required to safely bear the considerable forces and vibrations of the wind turbine. Once the foundation has been completed, the turbines are delivered and installed.
  • Laying medium- and low-voltage cables and fibre-optic cables: The electrical infrastructure connects the wind turbines to the grid and ensures that the energy generated is transmitted without interruption. Fibre-optic cables also enable continuous communication with and monitoring of the turbines.
  • Building a substation for the wind turbine: The substation is the heart of the electrical infrastructure and ensures that the energy generated can be fed into the grid. It regulates the voltage and stabilises the flow of electricity.
  • Testing and commissioning: In this final phase, the wind turbine is tested extensively to ensure that all components are working properly. After successful testing, the turbine is officially commissioned.

In addition to construction expertise, these phases require the support of engineering consultancies and specialist companies to ensure that all permits are in place and all formal and legal steps have been properly completed. Testing and site analysis are crucial to minimising potential operational risks.

Coordinating such an extensive project requires an experienced company that is able to manage all processes efficiently. This saves valuable time, avoids delays and makes the investment profitable sooner. Properly organising and managing all data saves investors money and enables faster commissioning of the turbine.

Wind turbine construction site at sunset

Construction of access roads and foundations

Before construction actually begins, a thorough soil investigation is required to assess the climatic and topographical conditions of the construction area. Unforeseen environmental factors can cause delays and additional costs or, in the worst case, jeopardise the entire wind project. Earthworks and foundation work require the use of heavy machinery, which needs stable access to the construction site.

In certain areas, such as road crossings or water obstacles, special permits are required to ensure that the construction work is coordinated with the local authorities. In addition, efforts are made to keep the wind turbine layout as compact as possible in order to minimise the area needed for construction. It is therefore essential to plan an efficient arrangement of all components as early as the planning phase. A compact layout not only saves construction costs but also simplifies the permitting procedure.

Access roads

Careful planning and construction of access roads is indispensable when building wind projects. These roads must be designed so that heavy construction and transport vehicles can reach the wind turbine sites without difficulty. Access to the turbines is particularly important during installation and later maintenance.

The ground must be adequately prepared before the access roads are built. A multi-layer sub-base stabilises the ground and ensures that heavy loads can be transported without difficulty, especially for deliveries by heavy goods vehicles. Alternatively, special ground reinforcement can be used to distribute the weight evenly and prevent wheels from sinking into the ground when it rains.

The width of the access roads must also be taken into account, as transporting large, bulky components such as the long rotor blades of modern wind turbines places special demands on the route. Rotor blades can currently be more than 50 metres long, so bend radii must be planned with particular care to allow sufficient space for the large transport vehicles. Existing infrastructure, such as telephone or power lines on poles, should also be taken into account when planning the access roads.

The gradient of the roads must also be considered. Steep inclines can make it difficult to bring the heavy turbine components to the construction site, so stable and safe access is an absolute prerequisite.

LEKO ENERGY: expertise in wind farm planning

Our team supports you every step of the way so that your wind projects can reach their full potential. We handle project planning, coordinate the expert reports and support you throughout the entire permitting procedure. Contact us.

Write us an email (opens your email program)

Foundation for the wind turbine

The permitting procedure under the Federal Immission Control Act (BImSchG) is at the heart of wind farm planning. It comprises several steps, from preparing the application documents to the final decision on the permit. The main challenge lies in the complexity and volume of the documents required. Delays often arise from incomplete applications or objections from local residents. Careful preparation and proactive solutions can minimise these obstacles.

The stability of a wind turbine depends crucially on its foundation. A faulty foundation can not only jeopardise the turbine’s operability but also lead to considerable financial losses. It is therefore important to carry out thorough geotechnical investigations of the site before construction begins. The geotechnical experts we commission analyse the condition of the soil and adapt the planning to the specific local conditions. Depending on the nature of the terrain, you may encounter soft soil that requires additional reinforcement or hard rock formations with a high load-bearing capacity.

Foundations for wind turbines can generally be divided into two types:

  • Shallow foundations: These foundations lie in the upper soil layers and are suitable for sites with sufficient load-bearing capacity or relatively low loads. A large bearing volume helps to distribute the forces evenly across the ground and ensures the stability of the turbine.
  • Deep foundations: If the subsoil has a low load-bearing capacity or the turbine is exposed to high forces, deeper foundations are used. These use piles, long concrete elements driven into the ground, which secure the stability of the turbine through their resistance to tensile, compressive and bending forces. Pile foundations offer a solution for sites that must withstand extreme loads and prevent structural damage to the turbine.

High-strength reinforced concrete is the preferred material for wind turbine foundations, as it meets the requirements for load-bearing capacity and resilience. The shape of the foundation varies depending on the site requirements. Circular layouts optimise the use of materials, while polygonal shapes, such as hexagonal or octagonal foundations, offer a larger contact area and absorb the resulting stresses well. Such shapes also reduce the need for additional reinforcement elements and make their use more efficient.

Special platforms are built in the immediate vicinity of the wind turbine to serve as work areas for maintenance and installation. These polygonal areas usually measure between 20 and 50 metres and provide sufficient space for the necessary work. Heavy cranes are used to build the platforms and the foundation, installing not only the turbine itself but also additional equipment such as transformers. The platform is also surrounded by wide access roads and storage areas for construction materials.

On a wind turbine construction site: excavators, engineers, construction workers

Installing the wind turbine

Installing a wind turbine is a precise and carefully coordinated process in which specialised cranes play a central role. Two cranes are usually used to erect the turbine: a main crane lifts and positions the heavy components, while an auxiliary crane helps to position and stabilise the individual parts.

  • Installing the tower segments: The tower of the wind turbine is assembled from several large segments. First, the lowest tower segment is anchored to the foundation. It forms the stable anchor point for the rest of the structure. The main crane then lifts one segment after another and positions it precisely on the section below, while the auxiliary crane ensures that each segment stays securely in place before it is fastened. With each new segment, the tower grows taller, which requires experienced crane operators and fitters, as occupational safety and the exact alignment of the segments are of the utmost importance.
  • Placing the nacelle on top of the tower: Once the tower is fully assembled, the nacelle, the heart of the turbine, is placed on top of it. The nacelle contains key components such as the gearbox and the generator. This step is particularly demanding, as the nacelle must be placed safely and accurately on the narrow top of the tower. The main crane lifts the nacelle slowly and carefully to the required height, while the auxiliary crane and experienced fitters stabilise it and move it into position.
  • Pre-assembly and attachment of the rotor blades: The rotor blades are usually pre-assembled with a hub on the ground so that they can later be attached to the nacelle as a complete unit. Two cranes are required for this step. The main crane lifts the rotor, while the auxiliary crane assists with exact positioning. This is a delicate process, as the large rotor blades are sensitive to wind and difficult to control.
  • Mounting the rotor on the nacelle: Once the rotor blades and the hub have been joined to form a complete rotor, the entire rotor is lifted and mounted on the nacelle. The main crane slowly raises the structure and carefully positions it in front of the nacelle opening, while the auxiliary crane brings the rotor into the correct alignment. This installation requires the utmost precision, as the rotor blades must be perfectly balanced and securely fastened to withstand the wind forces they will later be exposed to.

Well-thought-out site planning is essential to avoid losing time and to make crane operations efficient. All components and tools should be arranged so that they can be reached quickly and safely at any time. The main crane must be able to move large loads continuously, while the auxiliary crane simultaneously stabilises all components and ensures their exact alignment. Close cooperation between crane operators and installation experts is indispensable for the safe erection of the wind turbine, as any mistake could lead to considerable delays and additional costs.

Excavator on a wind farm construction site

Installation of the electrical systems and grid connection

The installation of a wind turbine’s electrical systems is crucial for feeding the energy produced into the power grid safely and efficiently. This includes installing transformers, laying medium-voltage cables and connecting to the control and monitoring infrastructure.

The transformers are installed in the immediate vicinity of the turbine to raise the low voltage generated to the higher voltage level required for feeding into the grid. These transformers convert the energy immediately after it is produced, minimising losses on the way to the substation.

Once the transformers have been installed, the medium-voltage cables connecting the turbine to the substation are laid. These cables are laid with great care to ensure reliable energy transmission over long distances. Owing to the long distances and high safety requirements, special protective measures and precise planning are necessary to prevent faults.

In addition to the medium-voltage cables, fibre-optic cables are installed to ensure continuous communication between the wind turbine and the central control systems. These fibre-optic cables enable real-time monitoring, so that every turbine in the wind farm can be continuously checked and, if necessary, controlled remotely. The control system can be operated both automatically and manually, which provides maximum flexibility and raises the standard of operational safety.

Connecting the turbine to the grid is the final step in the electrical infrastructure. This involves establishing the connection to the local substation, through which the energy generated is ultimately fed into the public grid. After extensive test runs and an inspection of all components, the wind turbine is officially commissioned and begins producing electricity.

On the construction site of a wind farm

Meteorological masts

Meteorological masts are indispensable for the operation and long-term efficiency of wind turbines. These masts collect detailed weather and wind data, which is crucial for planning, building and operating the wind turbine. Precise measurement of wind speed, wind direction and other climatic factors makes it possible to determine the optimum operating conditions for the turbine and to monitor its performance continuously.

The masts are erected in the immediate vicinity of the wind turbine to collect site-specific data. The information gathered is particularly valuable for understanding how local wind conditions change over time and helps to adjust turbine performance accordingly. Sensors on the mast record the data and transmit it in real time to the central control unit, enabling precise and rapid analysis.

The masts also contribute to the safety of the wind farm. Continuous monitoring of weather conditions means that automatic measures can be taken to protect the turbines in extreme weather. The data collected also helps with preventive maintenance, as it can provide indications of potential wear or stresses caused by variable wind conditions.

Without these masts and the data they provide, it would hardly be possible to operate the wind farm optimally and exploit the full capacity of the wind turbines.

Your project in safe hands: succeed with LEKO ENERGY

The energy transition is gathering pace, and the requirements for renewable energy projects are becoming increasingly complex. This is where LEKO ENERGY comes in: our experienced and dedicated team supports you every step of the way so that your wind or solar projects can reach their full potential. With our many years of experience and strong partnerships, we support you effectively and with a clear focus, from planning and permitting through to implementation.

Our approach is comprehensive: we take care of detailed project planning, coordinate all the required expert reports and support you throughout the entire permitting procedure. Our goal is to meet your requirements in full and to develop tailored, efficient solutions for your specific needs.

If you have already secured sites and need support with permits or project implementation, LEKO ENERGY is your reliable partner. With a broad network of experts and resources, we will take your project successfully over the finish line. Together, we will pave the way for a sustainable energy future.

Contact us today to turn your vision into reality: your success is our mission.

WE ARE HERE FOR YOU

Contact us

Potsdam
LEKO ENERGY GmbH Kirschallee 65 14469 Potsdam
Augustin Köllner
Sijar Hamid
Dr. Hannes Lenz
Tilman Herweg